APT Global Marine & Offshore Engineering (APT), UAE proudly announces the successful fabrication and delivery of two number Pre-Piling template for their prestigious client-DEME Offshore. This milestone underscores our commitment to delivering cutting-edge products that meet the evolving needs of our clients. Offshore substation foundations and offshore wind turbines installation in its initial stage will need to have the pin piles installed on the seabed. This execution will be performed using the self-levelling piling template which will be deployed overboard from an installation vessel into its designated location at the seabed. The piling template shall serve the following purposes:

 Allow stabbing of pin-piles and further driving in to designed depths.

 Allow for interface with drilling equipment.

1st unit Four-legged template

Overall dimension: L43.81m x W35.81m x H40.26m

Total Weight: 697T

Material Grades: NVE36

2nd unit Four-legged template

Overall dimension: L26.76m x W27.55m x H13.78m

Total Weight: 430T

Material Grades: NVE36

Class: DNV