This milestone underscores our commitment to delivering cutting-edge products that meet the evolving needs of our clients.Offshore substation foundations installation in its initial stage will need to have the pin piles installed on the seabed. This execution will be performed using the self-levelling piling template which will be deployed overboard from a floating vessel into its designated location at the seabed. The piling template shall serve the following purposes:
- Allow stabbing of pin-piles and further driving in to designed depths using Vibrohammer.
- Allow for interface with drilling equipment.
Template 1: Coastal Virginia Offshore Wind, USA
· Four legged template
· Overall dimension : L43.81m x W35.81m x H40.26m
· Total Weight: 697T
· Material Grades: NVE36
Template 2: Le Tréport Offshore Wind Farm Project
· Four legged template
· Overall dimension : L26.76m x W27.55m x H13.78m
· Total Weight: 430T
· Material Grades: NVE36
Class : DNV
The fabrication and delivery of the Pre-Piling templates involve a meticulous process to guarantee its quality, tolerance level and functionality requirements. By adhering to industry standard and project specifications, APT ensured timely delivery by following efficient and precise planning. This achievement is a testament to the dedication and expertise of our talented project team.
The ON TIME delivery of the templates marks a significant enhancement to the operational capability of our client, empowering them to meet the demanding requirements of piling operations for two large Offshore Windfarm installations. We extend our sincere gratitude to DEME Offshore for showing belief in APT.
As we continue with our efforts to innovate and modernize, meeting the high expectations of our clients, this accomplishment reinforces our position as a trusted provider of High Quality solutions in the Wind farm construction/installation industry.